normakte  /  Directive and Regulation compared

Machinery Directive vs Machinery Regulation: what changes

What stays, what is new and where the old annexes are now – point by point, with the reference in the official text.

Your technical file for the deadline: requirements with article references, evidence, declaration and nameplate in one place. Trial file free until 20.01.2027.Create a trial file

In brief

  • From 20 January 2027 Directive 2006/42/EC is repealed; references to it are construed as references to the Regulation (Art. 51(2)). There is no period in which either can be applied at will.
  • The principle stays the same: risk assessment, essential requirements, technical documentation, conformity assessment, declaration, CE marking.
  • The main changes: two groups of high-risk machinery, requirements on software, cybersecurity and self-evolving behaviour, autonomous mobile machinery, digital instructions and obligations for importers and distributors.
  • The annexes are reorganised: the essential requirements are now in Annex III, the list of high-risk machinery in Annex I.

The differences at a glance

TopicDirective 2006/42/ECRegulation (EU) 2023/1230Reference
Legal formdirective, transposed into national lawregulation, directly applicable in every Member StateArt. 54
Scopemachinery, interchangeable equipment, safety components, lifting accessories, chains, ropes and webbing, transmission devices, partly completed machinerymachinery and “related products” (interchangeable equipment, safety components, lifting accessories, chains, ropes and webbing, removable mechanical transmission devices) and partly completed machineryArt. 2(1)
Softwarenot expressly covered in the definition of machineryan assembly missing only the upload of the intended software is machinery; safety components can be digital, including software with a safety function placed on the market separatelyArt. 3(1)(f), 3(3)
High-risk machineryone list in Annex IVtwo parts: Annex I Part A (6 categories, always with a notified body) and Part B (19 categories)Art. 6, Annex I
Conformity assessmentinternal checks, EC type-examination, full quality assurancemodules A, B+C and H, new unit verification (module G); for Annex I Part A no internal production controlArt. 25
Essential requirementsAnnex IAnnex III, extended with protection against corruption, software in control systems, self-evolving behaviour, human-machine interaction and autonomous mobile machineryAnnex III 1.1.6, 1.1.9, 1.2.1, 1.3.7, 3.2.4
Technical documentationAnnex VIIAnnex IV (Part A for machinery, Part B for partly completed machinery); source code or programming logic on reasoned requestArt. 10(3), Annex IV
Declaration of conformityAnnex II, naming the person authorised to compile the technical fileAnnex V Part A; a single declaration for all acts; access also via internet address or machine-readable codeArt. 21, Art. 10(8)
Instructionspaperdigital allowed, online for at least ten years; paper on request at purchase; safety information always on paper for non-professional usersArt. 10(7)
Marking and contactname and address of the manufactureralso website, e-mail or other digital contact; a single contact point; year of construction = year the manufacturing process was completedArt. 10(5), (6)
Economic operatorsmanufacturer and authorised representativealso obligations for importers and distributors; traceability for ten yearsArts 13–17, 19
Substantial modificationnot defined in the Directivedefined; whoever carries it out is considered the manufacturerArt. 3(16), Art. 18
Post-market monitoring—sample testing, complaints, register of recalls, where appropriate in view of the risksArt. 10(4)

Where the old annexes are now

ContentDirectiveRegulation
Essential requirementsAnnex IAnnex III
EC/EU declarations of conformity and incorporationAnnex IIAnnex V
CE markingAnnex IIIArts 23, 24
High-risk machineryAnnex IVAnnex I
Safety components (indicative list)Annex VAnnex II
Assembly instructionsAnnex VIAnnex XI
Technical documentationAnnex VIIAnnex IV
Internal checksAnnex VIIIAnnex VI (module A)
Type-examinationAnnex IXAnnex VII (module B) with Annex VIII (module C)
Full quality assuranceAnnex XAnnex IX (module H)
Unit verification—Annex X (module G)

The full correspondence of articles is set out in the correlation table in Annex XII of the Regulation.

What stays the same

The process changes little. The manufacturer assesses the risks, identifies the applicable requirements, designs accordingly, compiles the technical documentation, chooses the procedure, draws up the declaration and affixes the CE marking. The order of protective measures – first by design, then technical, finally information – is the same (Annex III 1.1.2). A clean file under the Directive needs to be completed, not rewritten.

What happens to machinery under the Directive

Products placed on the market in accordance with the Directive before 20 January 2027 may continue to be made available. EC type-examination certificates issued under the Directive remain valid until they expire (Art. 52). What counts, for each individual unit, is the date of placing on the market.

Frequently asked questions

Can I work under the Regulation right away?

Until 19 January 2027 placing on the market is governed by the Directive, from 20 January 2027 by the Regulation. If you design today and deliver in 2027, build the Regulation’s requirements into the design and the file now.

Does my machine now need a notified body?

Only if it is listed in Annex I. For Part A always; for Part B only if harmonised standards or common specifications do not cover all relevant requirements. All other machinery stays with internal production control (Art. 25).

Does the Regulation apply to machinery I only use myself?

Yes. Whoever manufactures machinery and puts it into service for their own use is a manufacturer (Art. 3(18)(b)).

Do I need new harmonised standards?

Presumption of conformity applies to standards whose references are published in the Official Journal (Art. 20(1)). Check before the declaration which standards are published for the Regulation – the list under the Directive does not carry over automatically.

Run the transition in one file

Annex III requirements with evidence, Annex V declaration and nameplate in one place. Trial file free until 20.01.2027.

Create a trial file

Read next

Sources. Regulation (EU) 2023/1230, OJ L 165, 29.6.2023, including the corrigendum of 1.4.2025; Directive 2006/42/EC for the previous regime.

The information has been checked against the official text, paraphrased and shortened; only the official text is authentic.

normakte is a drafting and calculation aid; it replaces neither conformity assessment, nor a notified body, nor a technical assessment by a specialist, nor legal advice.

Further reading: other topics of the Machinery Regulation